Chevron lets contract for Nigerian Gas project

Chevron Nigeria Limited (CNL) has let a contract to Frames Group BV, Alphen aan den Rijn, in the Netherlands, to provide a natural gas dehydration unit for the 165-MMcfd Okan offshore gas gathering and compression platform (GGCP), which CNL 40% operates in Nigeria’s western Niger Delta region on behalf of partner Nigerian National Petroleum Corporation (NNPC) 60% under their Escravos gas project joint venture.

Frames’ scope of work will include design and construction of the glycol-based gas dehydration unit, which will be installed as part of an expansion of the GGCP’s existing dehydration system, the service provider said.

Expanded gas dehydration capacity at the platform comes as part of CNL’s Okan GGCP debottlenecking program to increase production from Okan field, Frames said.

This latest contract follows CNL’s April 2016 award to a consortium of NNCP subsidiary National Engineering & Technical Co. (Netco) and PAI Engineering Ltd. to deliver detailed engineering design (DED) services for the Okan GGCP debottlenecking project, which is intended to boost handling of additional non-associated gas (NAG) supply from new NAG wells CNL plans to drill as well as surplus NAG from the new Okan pig-receiver platform (PRP).

Designed to sustain Nigeria’s domestic gas supply, the Okan GGCP debottlenecking project will include:

Okan GGCP debottlenecking project located off Nigeria in about 25 ft of water within OML-96, Okan field’s GGCP currently dehydrates both AG from the Okan production platform and NAG from two NAG wells, OK-33 and OK-72.

Composed of three existing 55-MMcfd compressors, the Okan GGCP compresses and dehydrates AG in a nameplate 32-MMcfd triethylene glycol (TEG) gas contactor—currently operating at 57 MMcfd capacity—and routes it through a 20-inch pipeline to Escravos Gas Plant (EGP) Train 1’s slug catcher.

NAG used for gas lifting is routed through the lift-gas separator and TEG lift-gas contactor into Okan’s gas-lift network. With the most recent reservoir-deliverability forecast predicting a decline in rich gas supply to EGP Train 1, there is the need to increase Okan GGCP’s NAG-handling capacity to make up for the declining AG rate, Netco said.

According to current project plans, Okan GGCP’s existing 200-MMcfd glycol regeneration system will be replaced with a 320-MMscfd capacity regeneration system to allow for increased NAG-handling capacity.

Alongside NAG supplies arriving from new wells in Okan field, additional NAG will be routed to Okan GGCP via a 16-inch pipeline from the new Okan PRP, which receives excess NAG from Sonam NWP field.

Based on Netco’s June 2016 contract description, Netco and PAI Engineering’s scope of work on the Okan GGCP debottlenecking project will include delivery of DED for the following components:

For the Okan PRP portion of the project, the service companies will cover DED on the following:

 

A timeline for full start-up of the completed debottlenecking project is yet to be disclosed.